Scottish Water - Linwood Ave, Viaduct Rd, Overlee Park, Busby Glen - Work to commence January 2020 for 14 months
(1 viewing) (1) Guest
  • Page:
  • 1

TOPIC: Scottish Water - Linwood Ave, Viaduct Rd, Overlee Park, Busby Glen - Work to commence January 2020 for 14 months

Scottish Water - Linwood Ave, Viaduct Rd, Overlee Park, Busby Glen - Work to commence January 2020 for 14 months 1 month ago #1

  • RM64
  • OFFLINE
  • Platinum Boarder
  • Posts: 986
  • Karma: 1
What we are doing

Scottish Water as part of multi-million pound investment across the greater Glasgow area where we have transformed Glasgow's waste water systems will be carrying out significant upgrade to the sewer network in the Busby Glen area.

This work will reduce the risk of sewer flooding and provide environmental improvements to the local water courses.

Once complete, the new infrastructure will help prevent items which are wrongly flushed down the toilet, such as baby wipes and plastic cotton buds etc. from overflowing into the River White Cart Water.

It will also reduce the risk of sewer flooding to properties in the area as well as to Busby Glen Park.

When we are doing it

We anticipate the works will commence in January 2020 and will last approximately 14 months to complete, works in Busby Glen park will start January 2020 and will take roughly 8 months to complete.

Our alliance partners amey Black and Veatch (aBV) will be carrying out the works.

Information event

We are holding an information event to discuss our work and plans for the area, if you haven't received your invite and wish to attend and please feel free to come along the event will be on Wednesday 23rd October at Duff Memorial Hall G76 8DX from 3.30-7pm.

Find info here -

www.scottishwater.co.uk/en/In-Your-Area/...Your-Area/Busby-Glen

Re: Scottish Water - Linwood Ave, Viaduct Rd, Overlee Park, Busby Glen - Work to commence January 2020 for 14 months 1 month ago #2

  • RM64
  • OFFLINE
  • Platinum Boarder
  • Posts: 986
  • Karma: 1
The work is proposed to start in early 2020.

The work will take place in

Viaduct Road(Linwood Ave)

Overlee Playing Fields

Cartside Drive

Busby Glen Park

and

a section of Busby Road.


This will require part of Overlee Playing Fields to be closed,

the closure of Busby Glen Park

and sections of roads to be closed during the construction phase.