Re: Eastwood Park Leisure Centre 4 years, 10 months ago #295

  • Tom
  • OFFLINE
  • Platinum Boarder
  • Posts: 669
  • Karma: 36
I understand that there are some residents who are of the opinion that if this is voted through on Wednesday that they ought to thank the councillors.

Why?

These Cllrs from the Administration have put you through unnecessary trauma for over two years and cost the tax payer thousands of pounds.

Re: Eastwood Park Leisure Centre 4 years, 5 months ago #296

  • RM64
  • OFFLINE
  • Platinum Boarder
  • Posts: 3173
  • Karma: 19
Eventual update on Cleaning of Gym Changing rooms. A picture of the Dirty Grilles has been previously posted -

----- Original Message ------
To: "Whiteford, Andrew" < This e-mail address is being protected from spambots. You need JavaScript enabled to view it >
Sent: Thursday, 20 Jun, 2019 At 16:19
Subject: RE: Grille Photo

Hi

Re email below.

Can you give update on deep cleaning these grilles.

Thanks



Sent: 28 October 2019 11:40
To: Whiteford, Andrew
Subject: [SUSPECTED SPAM] Re: health/hygiene problem with grilles - please do not ignore

Hi

I did not receive a reply.

Please can you give an update on deep cleaning these grilles.

Thanks

------ Original Message ------
From: "Whiteford, Andrew" < This e-mail address is being protected from spambots. You need JavaScript enabled to view it >
Sent: Tuesday, 29 Oct, 2019 At 12:22
Subject: RE: [SUSPECTED SPAM] Re: health/hygiene problem with grilles - please do not ignore

Apologies that you did not receive the email response that I sent you.

It seems that we had an issue with outgoing email recently and have had problems contacting people out with our internal email system.

I had no notification that the response had not been delivered.

I can confirm that a full service of the air handling units took place back in April this year and staff carry out a clean and dust on the grilles on a daily basis and hoover the grilles on a weekly basis.

I will ensure that my Team Leaders are monitoring this to ensure it is being carried out.

This is the extent of what my staff are able to do, as we would not be in a position to remove grilles in any way, and the responsibility for plant/air handling equipment lies with the Council’s Property and Technical team, who arranged for the recent service to be carried out.

I have passed your comments on to our maintenance officer for discussion and any relevant action on his behalf.

I will be around the venue from 8:30am on Thursday, if you wish to ask for me via the front desk staff, and would be happy to discuss further.

Kind regards,

Andy Whiteford
Venue Manager
Eastwood Park Complex
East Renfrewshire Culture & Leisure Trust


Sent: 29 October 2019 14:37
To: Whiteford, Andrew
Subject: [SUSPECTED SPAM] RE:Re: health/hygiene problem with grilles

Hi Andy

Thanks for this.

If you look at them, you can see the dirt/dust/grime stuck under these grilles.

I would think the Grilles need to be removed in order for them to be deep cleaned.

I should be at the gym on Thursday and will ask for you.

Thanks


Sent: 31 October 2019 11:20
To: Whiteford, Andrew
Subject: [SUSPECTED SPAM] RE: RE:Re: health/hygiene problem with grilles

Hi Andy

It was good to meet up with you and talk.

I appreciate that you and your staff carry out a clean and dust on the grilles on a daily basis and hoover the grilles on a weekly basis but are not responsible for the deep clean of these grilles.

However, I would say that you as management are responsible for arranging the deep cleaning of these grilles.

Again, I am aware that this has to be done via the Council, but that does not mean that this deep cleaning should not be carried out.

As you did see, you can see the dirt/dust/grime stuck under these grilles. These grilles are also in the corridors and the Gyms.

It is well known that people are put off using these Council facilities due to the poor condition and health/hygiene problems concerning the changing rooms.

I think we should expect high standards regarding cleanliness, health/hygiene and all parts of these changing rooms should be clean.

Would appreciate if you would give me a date of when this deep cleaning will be undertaken.

Thanks


------ Original Message ------
From: "Whiteford, Andrew" < This e-mail address is being protected from spambots. You need JavaScript enabled to view it >
Sent: Thursday, 31 Oct, 2019 At 14:05
Subject: RE: [SUSPECTED SPAM] RE: RE:Re: health/hygiene problem with grilles

It was good to see you this morning and I agree with you when you say it is entirely my responsibility for arranging for a deep clean of the system, which I did do in April this year.

The council’s property and technical department are responsible for liaising with contractors and overseeing appropriate work in the venue where required.

The deep clean that took place was on the general system, filter replacements etc.

and not specifically on the vents/grilles.

I met with my maintenance officer this morning and have highlighted what is required, in more specific terms around vents/grilles, and he will instruct their approved contractor to come and carry out the works.

I do not have a date for this at the moment; however, I will certainly let you know when this is arranged for an keep you up to date with progress.

Thanks again for your time this morning and please do not hesitate to ask for me again should you wish to discuss further.

Kind regards,
Andy
Andy Whiteford
Venue Manager
Eastwood Park Complex
East Renfrewshire Culture & Leisure Trust

Re: Eastwood Park Leisure Centre 4 years, 5 months ago #297

  • RM64
  • OFFLINE
  • Platinum Boarder
  • Posts: 3173
  • Karma: 19
At the Council Meeting on 26 June 2019 a decision was taken based on these
Documents/reports to proceed with a new build leisure complex in Eastwood Park.

However after nearly 11 months NO documents/reports have been published.

This means the Council decision cannot be scrutinised.


Peter Brett Associates were given at least £49,000.00 of Council Tax Payers money and confirmed, to ERC, that for this £49,000.00 contract, they would produce Reports/Documents in regard to the Visioning & Masterplanning of Eastwood Park.

'28 January 2019 - Start
25 February 2019 - Visioning Report Draft
18 March 2019 - Visioning Report Final
1 April 2019 - Masterplan Draft
22 April 2019 - Masterplan Final
22 April 2019 - Action Plan / Road Map
The outputs for the project will include the following:

a. A Visioning report for the Campus – which outlines proof on concept – present & future uses, landscaping (hard & soft) and building enhancement potential.
b. Masterplan layout options for the site & presentation
c. Action plans/implementation road map/phasing with cost implications
d. Access and Transport review (including junction modelling & case for 2nd access and improved connections)
e. Community Benefits - details of how the new buildings will derive benefits for the Council and the wider community.
To enable delivery of above, PBA will utilise their multi-disciplinary team to provide planning, transport and economic inputs to the study.
This will be supplemented by Stallan Brand architects who will bring their significant architectural experience to assist in the design and visualisation of the masterplan options and the preparation of the visioning report and 3D images.'

A Freedom of Information request has been submitted and is now under review.

Re: Eastwood Park Leisure Centre 4 years, 5 months ago #298

  • RM64
  • OFFLINE
  • Platinum Boarder
  • Posts: 3173
  • Karma: 19
------ Original Message ------
To: This e-mail address is being protected from spambots. You need JavaScript enabled to view it
Cc: This e-mail address is being protected from spambots. You need JavaScript enabled to view it ; This e-mail address is being protected from spambots. You need JavaScript enabled to view it
Sent: Tuesday, 8 Oct, 2019 At 16:30
Subject: Freedom Of Information Request for Review - FOI Request 101002080925

Chief Officer (Legal and Procurement)
Council Headquarters
Rouken Glen Road
Giffnock
G46 6UG

REQUEST FOR FREEDOM OF INFORMATION(FOI) REVIEW

As instructed by Andrew Cahill, Director of Environment in their attached email dated 3 October 2019 (response to my FOI request dated 3 September 2019) and as Gerry Mahon, The Chief Officer Legal & Procurement, has previously stated that FoI is normally a 2 stage process -

'As you will be aware the Council's response to an FOI request does not merely revolve around the initial request but also the review process. It is hoped that any human error in relation to the 1st part of the process is properly remedied at the 2nd stage.'

I wish to request said FOI review.

My reasons for requesting FOI review are -

I completely disagree with the Director of Environment's reasons for withholding this information.

My understanding of the section 30(as per the Scottish Information Commissioner briefing paper) is that

B and C should not be used together for the same information.

In addition the public interest test must be laid out with pros and cons, and additional material arguments due to application of that exemption.

Although the exemption will often be applied to advice or to an exchange of views, it can apply to other types of information.

What is important is whether the disclosure would have an inhibiting effect on the provision of advice or on the exchange on views.

The Director of Environment has not provided any evidence that they have undertaken and/or applied a fair Public Interest Test.

This information should be published as East Renfrewshire Council has already made a decision based on this information.

The Director of Environment is denying East Renfrewshire Council Tax Payers the information to properly scrutinise the decision made by the Council.

It is my opinion any timescales for withholding have been exceeded including your own timescale of 6 to 8 weeks.

The Director of Environment says -

'The Council does hold further information received within the timescale of 29th May 2019 to 3rd September 2019.'

In order that the Director of Environment's decision can be properly scrutinised I would appreciate if the number and type of Information/Documents/reports etc referred to are provided.

I am of the opinion the Director of Environments interpretation is not correct.

I request that you review as -

Disclosure will not -

' inhibit substantially –

· the free and frank exchange of views for the purposes of deliberation; and

· would otherwise prejudice substantially, or be likely to prejudice substantially, the effective conduct of public affairs'.

Indeed, I would opinion that disclosure will enhance the free and frank exchange of views and enable scrutiny of the Council's decision.

Peter Brett Associates were given at least £49,000.00 of Council Tax Payers money and confirmed, to ERC, that for this £49,000.00 contract, they would produce Reports/Documents in regard to the Visioning & Masterplanning of Eastwood Park.


'28 January 2019 - Start
25 February 2019 - Visioning Report Draft
18 March 2019 - Visioning Report Final
1 April 2019 - Masterplan Draft
22 April 2019 - Masterplan Final
22 April 2019 - Action Plan / Road Map
The outputs for the project will include the following:

a. A Visioning report for the Campus – which outlines proof on concept – present & future uses, landscaping (hard & soft) and building enhancement potential.
b. Masterplan layout options for the site & presentation
c. Action plans/implementation road map/phasing with cost implications
d. Access and Transport review (including junction modelling & case for 2nd access and improved connections)
e. Community Benefits - details of how the new buildings will derive benefits for the Council and the wider community.
To enable delivery of above, PBA will utilise their multi-disciplinary team to provide planning, transport and economic inputs to the study.
This will be supplemented by Stallan Brand architects who will bring their significant architectural experience to assist in the design and visualisation of the masterplan options and the preparation of the visioning report and 3D images.'

It is now over 10 months and the Director of Environment has refused to publish any Documents/reports.

This despite the Council making a decision based on these Documents/reports at their meeting on 26 June 2019.

It would now appear that the Director of Environment is deleting these documents/reports received from Peter Brett Associates -

Andrew Cahill, the Director of Environment has said in a reply to Cllr David MacDonald - 'They were not retained as documents.'

This means that this Council decision cannot be scrutinised properly.

I wish to register my great concern over the deletion of reports/documents and request that you investigate the reasons for the deletion of these reports/documents.

Why should it not be concluded that the only reason Andrew Cahill, the Director of Environment is taking this course of action is to avoid Freedom of Information disclosure? -

- Receive reports/documents from company/consultants
- Claim a work in progress.
- The documents when finalized for the end report are then destroyed.
- The final report is never finished until the Director of Environment publishes it.

Yes a 'final report' can be produced, but the original documents that are used to compile this 'final report' are still valid and relevant and must be retained.

Please confirm that these reports/documents should be an asset and used in the future if required, to look at one specific subject(as they have not been copied in their entirety).

Please confirm that it is not convention to delete source documents - they are usually referenced in the final report.

Please confirm that destroying reports/documents has the effect of making the public suspicious as to the motive behind destruction - not in keeping with an open and transparent Council.

Is the Director of Environment not retaining/destroying these Reports/Documents because they don't like what is written in them?

If we cannot access them, how would we ever know?

These reports/documents should be retained.

There is no reason why these reports/documents should be destroyed.

It is now 08 October 2019 and it would appear not one document/report has been published.

As at the Full Council meeting on 26 June 2019 only 1 Document had been produced and the Director of Environment stated that this was 'in draft form, in the course of completion and is an unfinished document.'

As at 7 August 2019 Gerry Mahon, the Chief Officer, Legal & Procurement stated - ' the document is currently being sense checked and assessed for factual accuracy and consistency .......' and that it was still in draft form.

It is now over 10 months since the start of the project and nearly 7 months since the dates quoted by PBA for the completion of the documents.

The Director of Environment has published an email giving details of a further £2100.00 spend with Robinson Low Francis LLP - NQ71-ERC-02 Cost Information for Eastwood Park Masterplan

I would appreciate if you would give details of what documents/reports etc have been received for this spend and if they are also being withheld.

It is hard to believe that the Director of Environment has undertaken all this work on their own.

It is hard to believe they have had no contact with anyone else (except Hub West Scotland Ltd).

Again I would request that you review why this information has not been disclosed -

Correspondence/Emails/Letters/Contact/documents/reports etc between/to and from

East Renfrewshire Council (ERC)( Employees/Officers/Officials) and ERC( Employees/Officers/Officials)

ERC( Employees/Officers/Officials) and ERC Councillors

ERC( Employees/Officers/Officials) and Peter Brett Associates

ERC( Employees/Officers/Officials) and Others

Again, I would request that you review why no payment details and/or invoices have been provided.

I would request that the following is relevant and is considered and addressed in your review -

My understanding of the section 30(as per the Scottish Information Commissioner briefing paper) is that

B and C should not be used together for the same information.

In addition the public interest test must be laid out with pros and cons, and additional material arguments due to application of that exemption.

Although the exemption will often be applied to advice or to an exchange of views, it can apply to other types of information.

What is important is whether the disclosure would have an inhibiting effect on the provision of advice or on the exchange on views.

“Likely”

20. The exemptions in section 30(b) can only be applied where disclosure would, or would be likely to, cause substantial inhibition.

There must be at least a significant probability that substantial inhibition would occur in order for the exemption to be appropriately applied. There must be a genuine link between disclosure and inhibition: it cannot simply be a remote or hypothetical possibility.

“Substantial inhibition”

21. “Inhibit” is not defined in FOISA. This is the only exemption in FOISA where this terminology is used. In the context of section 30(b), it means to restrain, decrease or suppress the freedom with which opinions or options are expressed.

The inhibition caused by disclosing the information must be of real and demonstrable significance, rather than simply marginal, before the exemption can be applied.

Factors to consider

22. When assessing whether disclosure will cause substantial inhibition, an authority should consider the content of the information and the circumstances in which it was created.

I see no reason to believe that The Director of Environment has considered these facts.

Factors to consider may include:

(i) the identity or status of the author and/or the recipient. There may be an inherent sensitivity in the fact that advice or views were passed from one person to another, depending on the relationship between those parties. Where advice or views are communicated and received as part of an individual’s day-to-day professional functions, for example, then the risk of substantial inhibition may well be diminished.

(ii) the circumstances in which the advice or views were given. The context in which the communication took place might be relevant; for instance, views might be more sensitive during policy formulation or other discussions.

(iii) the sensitivity of the advice or views. The subject matter and content of the advice and opinions, as well as the way in which the advice or opinion is expressed, are likely to be relevant when determining whether the exemption applies.

23. See Appendix 1: Resources for examples of the Commissioner’s decisions on section 30(b).

A chilling effect?

24. Some public authorities have argued that disclosing any advice or views makes it inevitable that officials will conclude that other internal communications will probably have to be disclosed, thereby inhibiting the way in which advice or views are given in the future.

This is sometimes known as “the chilling effect”.

25. The Commissioner does not accept that the disclosure of advice or views in one case will have a substantially inhibiting effect in all others.

The exemptions in section 30(b) must not be treated as “class exemptions”. (Class exemptions – such as the exemptions in section 29 – allow information to be withheld if it falls into a particular category, e.g. Ministerial communications.)

With section 30(b), authorities must consider the content of the information before deciding whether disclosure would, or would be likely to, cause substantial inhibition.

26. The Commissioner believes officials are capable of understanding that some information of a particular type may be disclosed, while other information of the same type may be withheld, depending on the circumstances. Decisions are always taken on a case-by-case basis: disclosing advice or views in one case does not imply that information in another case will also have to be disclosed.

The Commissioner’s decisions since FOISA came into force back this up.

27. The Commissioner recognises that the general right of access provided by FOISA must be balanced against the need to protect genuinely sensitive information.

However, this does not justify a blanket exemption on all internal communications for fear that officials will react negatively to the release of information.

Instead, public authorities should assess the effect Page 5 of disclosing the information in question before applying either of the exemptions in section 30(b).

28. The Court of Session agreed with this approach in the case of Scottish Ministers v Scottish Information Commissioner [2006] CSIH 8 (see Appendix 1: Resources).

In their appeal, the Ministers argued that the Commissioner had erred in law by not recognising the possibility that, although the section 30 exemptions were not class based exemptions, they might apply to a class of documents, irrespective of the actual content of the documents.

The Court disagreed, saying that individual documents had to be scrutinised to establish whether they contain information which, when read in the context of related information, would, or would be likely to, have the specified harmful effect.

Only after such scrutiny is it possible to say whether the information concerned would, or would be likely to, have such an effect.


The public interest test


29. If the exemption applies, the authority must go on to consider the public interest in relation to the information – see section 2(1)(b) of FOISA.

This means assessing whether, in all the circumstances of the case, the public interest is better served by disclosing the information or maintaining the exemption.

The authority must identify and set out the competing arguments as to why the public interest would be served not only by disclosing the information, but also by withholding it.

Having identified the public interest arguments on each side, the authority must then carry out an exercise to determine where, on balance, the public interest lies.

There is an in-built presumption in FOISA that it is in the public interest to disclose information unless a public authority can show why there is a greater public interest in withholding the information.

30. FOISA does not define the term “public interest”, but it has been described as “something which is of serious concern and benefit to the public.”

It has also been said that the public interest does not mean what is of interest to the public, but what is in the interest of the public.

The Commissioner has published guidance on the public interest test – see Appendix 1: Resources.

31. There is clearly a strong public interest in protecting the effective conduct of public affairs.

The Commissioner has generally found that this public interest outweighs the public interest in disclosure of information where the effective conduct of public affairs is, or is likely to be, substantially harmed.

However, there have been a few cases where a strong public interest in disclosure has swung the balance in favour of disclosure.

For an example of a decision where this happened, see Appendix 1: Resources. Section 30(c) – the effective conduct of public affairs

32. Information is exempt under section 30(c) of FOISA if disclosure would otherwise prejudice substantially, or be likely to prejudice substantially, the effective conduct of public affairs.

The use of “otherwise” makes it clear that the exemption can’t be used to withhold information where disclosure would harm the maintenance of collective responsibility or inhibit the free and frank exchange of advice or views.

In those cases, section 30(a)/(b) should be applied instead. (Of course, in some cases the exemptions may also apply but for different reasons.)

33. This makes it extra important, when applying the exemption, for authorities to demonstrate how and why disclosure would harm the effective conduct of public affairs.

Authorities should be able to explain which aspects of their business would be affected, and in what way, and be able to show why this outcome would result from disclosure of the information requested.


I understand that it is my right to have a response within 20 working days....a prompt response will be much appreciated.

I would appreciate if you would acknowledge receipt of this Request for Review.

Thanks

Re: Eastwood Park Leisure Centre 4 years, 4 months ago #299

  • RM64
  • OFFLINE
  • Platinum Boarder
  • Posts: 3173
  • Karma: 19
COUNCIL MEETING - Wednesday 18 December 2019 at 7.00 pm

AGENDA ITEM 11

11.Eastwood Leisure Centre and Masterplan - Report by Director of Environment (copy attached, pages 113 – 152).

You can read the paper/report here -

www.eastrenfrewshire.gov.uk/CHttpHandler.ashx?id=25658&p=0



TO:
Provost Fletcher; Deputy Provost Cunningham; and Councillors Aitken, Bamforth, Buchanan, Convery, Devlin, Gilbert, Grant, Ireland, Lafferty, Macdonald, McLean, Merrick, Miller, O’Kane, Swift and Wallace.

EAST RENFREWSHIRE COUNCIL

A meeting of the East Renfrewshire Council will be held within the Council Chamber, Council Headquarters, Eastwood Park, Giffnock,

on Wednesday 18 December 2019 at 7.00 pm.

Re: Eastwood Park Leisure Centre 4 years, 4 months ago #300

  • RM64
  • OFFLINE
  • Platinum Boarder
  • Posts: 3173
  • Karma: 19
Eastwood Park Masterplan

Quick Overview of Cost

Option 1 - Retain Existing HQ Building / New Leisure Centre with Landscaping
£31,200,000 Total Construction Cost - Option 1
£7,500,000 Allowance for Loose Furniture, fixtures, and equipment(FF&E), Risk, Fees & Development Costs
£?,???,??? Running Costs
£?,???,??? Maintenance Costs

Option 1A - Retain Existing HQ Building / New Leisure Centre with Civic Hub
£39,100,000 Construction Cost Total -Option 1A
£9,500,000 Allowance for Loose FF&E, Risk, Fees & Development Costs
£?,???,??? Running Costs
£?,???,??? Maintenance Costs

Option 2-Demolish Existing HQ Building with Car Park / New Leisure Centre with Civic Hub
£40,000,000 Construction Cost Total-Option 2
£9,700,000 Allowance for Loose FF&E, Risk, Fees & Development Costs
£?,???,??? Running Costs
£?,???,??? Maintenance Costs

Option 2A-Retain Existing HQ Building Demolish Existing HQ Building replace with 5-aside Pitch with Rooftop Car Park & Leisure Centre with Civic Hub
£42,000,000 Construction Cost Total-Option 2A
£10,200,000 Allowance for Loose FF&E, Risk, Fees & Development Costs
£?,???,??? Running Costs
£?,???,??? Maintenance Costs


Breakdown of Cost

£31,200,000 Option 1 – Retain Existing HQ Building / New Leisure Centre with Landscaping

£27,900,000 New Build Leisure Centre and Theatre (8,000m2 GIFA)

£300,000 Reconfigure Existing Leisure Centre Car Park to Incorporate Drop Off

£1,700,000 New School Staff Car Park in Existing Allotment Area

£600,000 Demolish Existing Leisure Centre and Theatre Building

£ 700,000 New Central Public Realm on Site of Existing Leisure and Theatre Building

£31,200,000 Total Construction Cost - Option 1

£7,500,000 Allowance for Loose Furniture, fixtures, and equipment(FF&E), Risk, Fees & Development Costs



£39,100,000 Option 1A –Retain Existing HQ Building / New Leisure Centre with Civic Hub(£)

£27,900,000 New Build Leisure Centre and Theatre (8,000m2 GIFA)

£300,000 Reconfigure Existing Leisure Centre Car Park to Incorporate Drop Off

£1,700,000 New School Staff Car Park in Existing Allotment Area

£800,000 Demolish Existing Leisure Centre and Theatre Building and School Sports Halls

£700,000 Build New Central Public Realm on Site of Existing Leisure and Theatre Building

£7,700,000 New Civic Hub between School and Leisure Centre (3,200m2GIFA)

£39,100,000 Construction Cost Total -Option 1A

£9,500,000 Allowance for Loose FF&E, Risk, Fees & Development Costs



£40,000,000 Option 2–Demolish Existing HQ Buildingwith Car Park / New Leisure Centre with Civic Hub

£27,900,000 New Build Leisure Centre and Theatre (8,000m2 GIFA)

£1,700,000 New School Staff Car Park in Existing Allotment Area

£1,400,000 Demolish Existing HQ Office, Leisure Centre, Theatre & School Sports Halls

£ 600,000 New Drop Off and Car Park Area on Existing HQ Site

£700,000 New Central Public Realm on Site of Existing Leisure and Theatre Building

£7,700,000 New Civic Hub between School and Leisure Centre (3,200m2GIFA)

£40,000,000 Construction Cost Total-Option 2

£9,700,000 Allowance for Loose FF&E, Risk, Fees & Development Costs




£42,000,000 Option 2A–Retain Existing HQ Building Demolish Existing HQ Building replace with 5-aside Pitch with Rooftop Car Park & Leisure Centre with Civic Hub

£27,900,000 New Build Leisure Centre and Theatre (8,000m2 GIFA)

£1,700,000 New School Staff Car Park in Existing Allotment Area

£ 1,400,000 Demolish Existing HQ Office, Leisure Centre, Theatre & School Sports Halls

£2 ,600,000 New covered 5-a-side pitches with rooftop parking

£700,000 New Central Public Realm on Site of Existing Leisure and Theatre Building

£7,700,000 New Civic Hub between School and Leisure Centre (3,200m2GIFA)

£42,000,000 Construction Cost Total-Option 2A

£10,200,000 Allowance for Loose FF&E, Risk, Fees & Development Costs



Potential Additional Items(£)

£200,000 Demolish Existing School Sports Halls

£600,000 New Public Realm between School and Leisure Centre (For Option 1 only)

£ 2,000,000 Refurbish and Extend Eastwood House

£900,000 Convert Existing Age Concern facility to Cycle Hub and Café*

£400,000 Upgrade woodland paths, pedestrian access routes, surfacing, lighting and signage

£200,000 Extend promenade from central public space to proposed new nursery building

£200,000 Form new pedestrian gateway access to South West corner of park

£100,000 Lower stone wall along full length of Roukenglen Road by 1m

£1,300,000 New car park south of community campus (in lieu of allotments)

*Potential current Age Concern Building could be sold to an external café operator to generate a capital receipt

Notes on Costs
•Construction Costs are inclusive of External Works, Fixed Furniture, Preliminaries and Overheads and Profit.
•Total Development Costs are inclusive of Loose Fittings and Furnishings, Risk, Professional Fees and Developer / Finance Costs. We have excluded the following items which will be required for the total Project costs;
Value Added Tax
Inflation beyond Q2 2019 pricing levels(see table in section 10.5)
Land acquisition costs and fees


£?,???,??? Running Costs
£?,???,??? Maintenance Costs