20 January 2020 - Viaduct Road and Linwood Ave (part of) closed for a period of Approx 12 months - Local access to be provided for residents only
(1 viewing) (1) Guest
  • Page:
  • 1
  • 2

TOPIC: 20 January 2020 - Viaduct Road and Linwood Ave (part of) closed for a period of Approx 12 months - Local access to be provided for residents only

Re: 20 January 2020 - Viaduct Road and Linwood Ave (part of) closed for a period of Approx 12 months - Local access to be provided for residents only 4 years, 1 month ago #7

  • RM64
  • OFFLINE
  • Platinum Boarder
  • Posts: 3164
  • Karma: 19
Linwood Ave

In addition Leaflet thru door from Scottish water

Turning off water -

Monday 10 February 2020

09:00 to 14:00

Re: 20 January 2020 - Viaduct Road and Linwood Ave (part of) closed for a period of Approx 12 months - Local access to be provided for residents only 4 years, 1 month ago #8

  • RM64
  • OFFLINE
  • Platinum Boarder
  • Posts: 3164
  • Karma: 19
To: "Scottish Water" < This e-mail address is being protected from spambots. You need JavaScript enabled to view it >
Received: Sun Feb 02 2020 12:11:06 GMT+0000 (Greenwich Mean Time)
Subject: Urgent - Weekend Work Linwood Ave/Viaduct Rd - ‘Capital/aBV/401705’

**EXTERNAL MAIL** - Think Before You Click

Hi

I refer to below regarding weekend work.

What are the working hours?

- We will be working Monday to Friday from 8am to 6pm.

- If we are required to work weekends we will letter you in advance.

We did not receive any advance letter.

We were assured we could park where possible outside our houses at the weekends.

Work would only take place Monday to Friday 8am - 6pm.

However today Sunday 02/02/2020 Huge lorries, vans, pipes negotiating up/down Linwood Ave.

Can you clarify the situation.

Thanks

------ Original Message ------
From: "Scottish Water" < This e-mail address is being protected from spambots. You need JavaScript enabled to view it >
Sent: Sunday, 2 Feb, 2020 At 15:48
Subject: RE: Urgent - Weekend Work Linwood Ave/Viaduct Rd - ‘Capital/aBV/401705’

I have forwarded your email on to our Capital Projects department to look into this further for you.

Once we receive an update, we will contact you.

Kind regards,
Customer Engagement Centre | Customer Service

------ Original Message ------
To: "Scottish Water" < This e-mail address is being protected from spambots. You need JavaScript enabled to view it >
Sent: Monday, 3 Feb, 2020 At 17:03
Subject: Re: RE: Urgent - Weekend Work Linwood Ave/Viaduct Rd - ‘Capital/aBV/401705’

Hi

When can update be expected?

Thanks

------------------- Original Message -------------------
Received: Thu Feb 06 2020 11:55:45 GMT+0000 (Greenwich Mean Time)
To: ;
Subject: Re: RE: Urgent - Weekend Work Linwood Ave/Viaduct Rd - ‘Capital/aBV/401705’

Hi

As it's nearly the weekend, when can update be expected?

Thanks

------ Original Message ------
From: "Scottish Water" < This e-mail address is being protected from spambots. You need JavaScript enabled to view it >
Sent: Saturday, 8 Feb, 2020 At 10:41
Subject: Re: RE: Urgent - Weekend Work Linwood Ave/Viaduct Rd - ‘Capital/aBV/401705’

Please accept our sincere apologies for the delay in responding to your email.

I can advised this was passed to the contractors ABV, I am requesting that our Capital Projects department contact them for an update.

We will contact you as soon as we receive further information.

Kind regards,
Customer Engagement Centre | Customer Service


------ Original Message ------
From: "McCann, Allan" < This e-mail address is being protected from spambots. You need JavaScript enabled to view it >
Sent: Monday, 10 Feb, 2020 At 12:24
Subject: aBV / Scottish Water - Weekend working Advice

I write in relation to your recent correspondence with Scottish Water with regards to the fact that there were works being completed over the course of the past couple of weekends.

Firstly, please accept or apologies for no letter/postcard being received ahead of these works.

This should have been sent out to yourselves.

Going forward however, please note that weekend working will be kept to a minimum.

We have had to work at the weekend recently due to issues we have encountered with regards to a water main diversion.

The water main diversion was a necessity to be completed ahead of the upgrading to the sewer network itself.

We therefore worked these Sundays in an attempt to minimise any future problems and to ensure the sewer upgrade itself still maintains construction programme.

We have now resolves these issues with the diversion looking to be completed by Tuesday 11th February.

I also understand that there may have been frustration with what appears to be minimal progress on the site.

This is due to the required methodology during the installation of a water main diversion where the new main needs to be left for a period of time during which time the pressure is tested, it is disinfected, sampling of the water is completed and there are also a number of days in which the results of any samples taken to be returned.

As such, it may look like not much progress is being made but we need to abide by the timescales as set out to ensure the new water main is safe.

Trust that this explains the situation however do not hesitate to call me on the number below.

Allan
Allan McCann / Programme Project Manager
aBV Pavilion 2/2, Buchanan Gate Business Park,
Stepps, Glasgow, G33 6FB
amey-Black & Veatch is a Joint Venture of Byzak Limited (trading as amey) and Black & Veatch Limited.
Byzak Limited Registered Office: Chancery Exchange, 10 Furnival Street, London, United Kingdom, EC4A 1AB; Registered in England & Wales No. 01809458.
Black & Veatch Limited Registered Office: 60 High Street, Redhill, Surrey RH1 1SH; Registered in England & Wales No. 3163649
Amey plc is a company registered in England and Wales. Registered Office: Chancery Exchange, 10 Furnival Street, London, EC4A 1AB. Registered Number: 4736639. For particulars of companies within the Amey Group, please visit www.amey.co.uk/Home/Companyparticulars/tabid/182/Default.aspx.

Re: 20 January 2020 - Viaduct Road and Linwood Ave (part of) closed for a period of Approx 12 months - Local access to be provided for residents only 3 years, 1 month ago #9

  • RM64
  • OFFLINE
  • Platinum Boarder
  • Posts: 3164
  • Karma: 19
Yes, the work is still on going !

Re: 20 January 2020 - Viaduct Road and Linwood Ave (part of) closed for a period of Approx 12 months - Local access to be provided for residents only 3 years, 1 month ago #10

  • RM64
  • OFFLINE
  • Platinum Boarder
  • Posts: 3164
  • Karma: 19
------ Original Message ------
To: "*Roads" <* This e-mail address is being protected from spambots. You need JavaScript enabled to view it >
Sent: Tuesday, 2 Feb, 2021 At 12:34
Subject: Re:  Mail Ref  - Viaduct rd/Linwood Avenue - Surfacing/footway & Street Lighting -  Over A Year On - Current Update February 2021

Hi Jane

Please see below update from Scottish Water.

As a completion time has been given - April 2021 would appreciate if you can give an update on the following(as any negotiations and plans by ERC would need to be  put in place fairly soon to meet this date?) -

Have you or any Council Official visited the site yet?

Extent of Road Resurfacing(Viaduct Rd, Linwood Ave, Overlee Rd) to be carried out by Scottish Water

Extent of Road Resurfacing (Viaduct Rd, Linwood Ave, Overlee Rd) to be carried out by East Renfrewshire Council(ERC)

Construction of footway on Viaduct Road

'With regards to the possibility of the additional length of footway being constructed on Viaduct Rd again due to lock down restrictions  on our staff carrying out site visits this has not yet been progressed but our traffic team still have this on their list and if it is considered feasible it would be the intention that any works would be co-ordinated with the Scottish water resurfacing of  Viaduct Road. I will update you regarding this as soon as possible'

Again, your help is much appreciated.

Thanks

------ Original Message ------
To: This e-mail address is being protected from spambots. You need JavaScript enabled to view it
Sent: Tuesday, 2 Feb, 2021 At 12:08
Subject: BV / Scottish Water - Linwood Ave/Viaduct Road -  Sewer Works - Over A Year On - Current Update February 2021

Hi

You may be interested(or may not) in our latest update below.

This was posted on Cllr David MacDonalds facebook page a couple of weeks ago.

'Jan Millar It’s  so good to see the reactions of people about Eastwoodmains Road. We on  Viaduct Road have now had over a year of total disruption. Only Scottish  Water kept us informed. It’s still not completed we are now told April  will be the completion date. No message from Council or Councillors.'


Sums it up.

Thanks

------ Original Message ------
From: "Borthwick, Ross" < This e-mail address is being protected from spambots. You need JavaScript enabled to view it >
Cc:  " This e-mail address is being protected from spambots. You need JavaScript enabled to view it " < This e-mail address is being protected from spambots. You need JavaScript enabled to view it >;  " This e-mail address is being protected from spambots. You need JavaScript enabled to view it " < This e-mail address is being protected from spambots. You need JavaScript enabled to view it >
Sent: Tuesday, 2 Feb, 2021 At 11:08
Subject:  RE: Important - RE: cas-1267863 - BV / Scottish Water - Linwood  Ave/Viaduct Road - Sewer Works - Current Update - February 2021?

Please find attached letter that is due to be delivered today.

As you will see the tunnelling works are due to commence this coming Monday, 08/02/21.

Our current programme has us completing all work on Viaduct Road and Linwood Ave by the middle of April.

Thanks,
Ross Borthwick | Sub Agent
Buchanan Gate Business Park,
Stepps, Glasgow, G33 6FB


Important Information from Scottish Water

Project reference
Capital/401705/aBV
Our alliance partner amey Black & Veatch  shall manage this work on our behalf.

2nd February 2021
Dear Customer


Taking care of your Sewer Network in Clarkston.

Customer Update

As of 8st of February the tunnelling works from Overlee Park to Viaduct Road will commence.

Conditions imposed by Network Rail mean this work will be running 24 hours per day for 5 days, whilst working under their asset.


All tunnelling operations are performed from the drive shaft within Overlee Park.

Noise and vibration monitoring will continue throughout the work.

Removal of the tunnelling machine will require a crane to be positioned on Viaduct Road, this will take place under normal working hours.    

We would like to thank you for your continued patience and understanding whilst we complete these essential works.

Yours Sincerely & on behalf of Scottish Water
Nicole McColgan
Amey-Black & Veatch Communications Advisor.



------ Original Message ------
From: "*Roads" <* This e-mail address is being protected from spambots. You need JavaScript enabled to view it >
Sent: Wednesday, 5 Aug, 2020 At 16:57
Subject: FW: Mail Ref  -Viaduct rd/Linwood Avenue - Surfacing/footway & Street Lighting

As I think you will be aware the works in the area being carried out by Scottish Water have suffered considerable delay due to the  COVID restrictions on the construction industry and there revised completion date has been pushed back until the end of April 2021.

Similarly our own planned programme of resurfacing works for 2020/21 has been affected and several schemes have now been deferred  until next financial year, Overlee Road and Linwood Avenue included.

They are included in our draft programme of works for 2021/22 subject to final assessment later this financial year and of course confirmation of budgets for financial year 2021/22 and it  would be my intention to carry out the works upon completion of the Scottish Water works early in the new financial year if possible.

With regards to the possibility of the additional length of footway being constructed on Viaduct Rd again due to lock down restrictions  on our staff carrying out site visits this has not yet been progressed but our traffic team still have this on their list and if it is considered feasible it would be the intention that any works would be co-ordinated with the Scottish water resurfacing of  Viaduct Road.

I will update you regarding this as soon as possible,
Regards
Jane
Jane Corrie
Roads & Transportation Controller
East Renfrewshire Council

Re: 20 January 2020 - Viaduct Road and Linwood Ave (part of) closed for a period of Approx 12 months - Local access to be provided for residents only 3 years, 1 month ago #11

  • RM64
  • OFFLINE
  • Platinum Boarder
  • Posts: 3164
  • Karma: 19
Sent: 05 August 2020 12:05
To: *Roads <* This e-mail address is being protected from spambots. You need JavaScript enabled to view it >
Subject: Re: 2124379 - Viaduct rd/Linwood Avenue - Surfacing/footway & Street Lighting

Hi Jane

As details of future road re-surfacing works have been published in the Barrhead News, can you give me an update on the progress of re-surfacing of Linwood Ave when the current water/sewer works are completed
and on below -

In respect of the potential for installing a new footway on the south side of Viaduct Rd as indicated, our Traffic team have added this to their  list of potential schemes however they have not as yet progressed with any feasibility/costing exercise which they hope to be able to do in the next few weeks.

They will also liaise with Scottish Water regarding their works programme  for the resurfacing of Viaduct Road as it would be hoped that if construction of a new footway is viable then it could possibly be carried out in conjunction with that work.

Hope you have been able to visit the site.

Keep well
Thanks



------ Original Message ------
To: "*Roads" <* This e-mail address is being protected from spambots. You need JavaScript enabled to view it >
Sent: Thursday, 12 Mar, 2020 At 14:16
Subject: Re: FW: 2124379 - Viaduct rd/Linwood Avenue - Surfacing/footway & Street Lighting

Hi Jane

Thanks for your response.

It is disappointing that it is now March and you have been unable to visit the site.

A case of 'out if site(sic) out of mind' !

If you do visit, you can knock our door. We would be pleased to give you a cup of tea.

Anyway, you are not the only one to not visit.

Our local councillors Lafferty, Ireland, Miller and MacDonald all seem to have forgotten we exist.

No-one seems to be bothered with our inconvenience now.............

But, we will cope with being soaked making the several trips carrying the shopping etc round to our blocked off houses.

Good news about the old lamppost holes though.

Would appreciate if you can keep me up to date with feasibility/costing exercise of new footway and resurfacing of roads(including Linwood Ave ).

Thanks



------ Original Message ------
From: "*Roads" <* This e-mail address is being protected from spambots. You need JavaScript enabled to view it >
Sent: Tuesday, 10 Mar, 2020 At 13:40
Subject: FW: 2124379 - Viaduct rd/Linwood Avenue - Surfacing/footway & Street Lighting

Apologies for the delay in my response, I had hoped to be able to visit site myself before responding  to you but as yet have been unable to do so.

With regards to the reinstatement of the footways where the old lighting columns have been removed  this matter has been raised with our contractor and they have been asked to carry out proper reinstatement of these areas as soon as possible.

In respect of the potential for installing a new footway on the south side of Viaduct Rd as indicated,  our Traffic team have added this to their list of potential schemes however they have not as yet progressed with any feasibility/costing exercise which they hope to be able to do in the next few weeks.

They will also liaise with Scottish Water regarding their  works programme for the resurfacing of Viaduct Road as it would be hoped that if construction of a new footway is viable then it could possibly be carried out in conjunction with that work.

Regards
Jane

Re: 20 January 2020 - Viaduct Road and Linwood Ave (part of) closed for a period of Approx 12 months - Local access to be provided for residents only 3 years, 1 month ago #12

  • RM64
  • OFFLINE
  • Platinum Boarder
  • Posts: 3164
  • Karma: 19
Important Information from Scottish Water

Project reference
Capital/401705/aBV
Our alliance partner amey Black & Veatch shall manage this work on our behalf.

2nd February 2021
Dear Customer


Taking care of your Sewer Network in Clarkston.

Customer Update

As of 8st of February the tunnelling works from Overlee Park to Viaduct Road will commence.

Conditions imposed by Network Rail mean this work will be running 24 hours per day for 5 days, whilst working under their asset.


All tunnelling operations are performed from the drive shaft within Overlee Park.

Noise and vibration monitoring will continue throughout the work.

Removal of the tunnelling machine will require a crane to be positioned on Viaduct Road, this will take place under normal working hours.

We would like to thank you for your continued patience and understanding whilst we complete these essential works.

Yours Sincerely & on behalf of Scottish Water
Nicole McColgan
Amey-Black & Veatch Communications Advisor.