COST OF INITIATIVES
East Renfrewshire "Bike & Roll" Corridors; outline costs
Scheme
Total Length (m)
Total Cost (high-Level)
Lower end costs (estimate)
Additional expenditure
Funding request
A77 Fenwick Road
1796
£112,135
£90,000
Additional civils for bus stop accessibility. Sustainable Transport Corridors (Giffnock). Light segregation - wands.
£100,000
A727 Eastwood Toll
1326
£81,058
£50,000
Temp crossing facility Rouken Glen Road - Park
£60,000
*Clarkston to Netherlee
2200
£137,155
£100,000
Additional civils for bus stop accessibility & restricted crossing. Light segregation - units.
£130,000
*A77 Ayr Rd & Eastwood Toll
8000
£498,720
£350,000
Eastwood Toll (cones & signage solution). Additional civils for bus stop accessibility. Light segregation - wand.
£400,000
* Average total cost (high level) / 100m = £6,234
Additional spend (to be supported by any underspend from above)
Proposal
(Estimate)
(Estimate)
(Estimate)
Glasgow City Council allocation A77 (ERC boundary - Shawlands)
£100,000
£100,000
£100,000
School Travel walking/cycling bus (staff costs) & support
£30,000
£30,000
£30,000
School Zones collapsible bollards around schools - operational am/pm peak
£50,000
£50,000
£50,000
Neighbourhood Zones/Active Travel routes strategic road closures & temporary AT measures to support proposals
£50,000
£50,000
£50,000
Town Centre Travel MapsPromotional material to support economic recovery plan
£10,000
£10,000
£10,000
Total: £1,069,068 £830,000 £930,000